It was early January. The beginning of 2016 had been work-filled. We were all terribly busy, as we had several overlapping jobs to carry out.

There was the Mega-Fixu automated dispensing system delivery to HUS Pharmacy, the construction of the automated hospital system for the Lahti hospital pharmacy in our hall and three automated system installation jobs at pharmacies across Finland.

Then there was the automated system for the Seinäjoki Central Hospital, which we had disassembled and loaded onto trucks during the previous week. We had agreed with the transport company that our boys would unload the truck in Seinäjoki on Monday afternoon.

The boys headed for Seinäjoki in the morning and made it to their destination at noon. Soon, I received an unpleasant phone call: the driver had broken the slide rails while unloading the truck. At first, I thought it couldn’t be possible and that the boys were just playing around. But it so happened that the driver had taken it upon himself to unload the truck and dragged the over 10 metres long and rather heavy rails across the yard. We usually have four men carrying them. It is important to take care when unloading them. This illiterate Estonian driver had not been able to read the instructions in the consignment note.

The damage turned out to be substantial, the total costs, with all the work included, amounted to almost €100,000.

After cursing for a while, we began clearing up the matter. We asked the boys to take some photographs and examine how many components were broken. The damage turned out to be substantial, the total costs, with all the work included, amounted to almost €100,000. My colleague Timo contacted the insurance company, who sent an insurance inspector to take a look at the damage. Unfortunately, the damage was covered by the transport company’s insurance, in which the compensations are based on the weight. It did not cover all the expenses, only a small part of them.

After inspecting the damage, we immediately began calling the component suppliers and charting how soon we could have replacement parts. The frame profile supplier near Seinäjoki promised to deliver replacement parts in a couple of days, while the slide rails arrived from Germany in a couple of weeks. Luckily, the factory of our German partner has an emergency function that enables them to bypass other production, if necessary. Otherwise, we would have had to wait for months for the parts.

Next, we had to start re-thinking the installation plan, so that the installation team would have work the entire time and we could remain on schedule. You could say that we had to make the decorations before baking the cake. Usually we start by building the most important part, which is the storage into which the rails are attached. Now we had to start the construction from the last installation phase, which is the conveyer line. This slowed us down and resulted in extra work. We had to make measurements and try to visualise where which part would go. However, our experienced installation team did a very good job, even though it is difficult to do precise work without the parts.

I told the customer and the construction contractor about the damage at our site meeting. I assured them that we would stay on schedule, even though we had not prepared for something like this. We promised to change the installation plan and work over weekends to avoid any delays. It ended up being very close, but we managed to reach the main goals of the schedule. For the customer, this “crisis” was not even very noticeable.

Nothing like this had ever happened before. But we pulled through in the end ‒ thanks to our skilled work team.

More information

Kauko Hynninen
Project and Commissioning Manager
Worked at NewIcon for 5 years

 

Site: Hospital pharmacy of the Seinäjoki Central Hospital, new building
Order: September 2015
Mechanical installation: week 1 / 2016
System start up and technical testing: week 6 / 2016
System qualification: week 9 / 2016
Process validation: week 11 / 2016
User training and user testing: week 10 / 2016
Commissioning: week 28 / 2016

 

The article was originally published in the Icon News magazine in 2016.

 

Read more about our products:

For hospitals

For retail pharmacies

 

Would you like to stay updated on the latest news? Subscribe to our newsletter.